Installation process of YX60-490 color steel roof panel in steel structure factory building:

In China, new industrial production projects have increasingly high requirements for steel structure factories. The steel structure workshop has the advantages of simple construction, short construction period, high utilization rate, and comprehensive utilization rate. The tiles that conform to the color steel bending structure also have advantages such as easy installation, easy disassembly, waterproofing, and good insulation, and have received praise from many customers.

1. The installation steps for the color steel roof are as follows: install the lower mesh plate → install the eaves rain shield and the next layer ridge plate → lay insulation materials → install the top steel plate → install the rain shield and sealing plate → sealant.

2. When lifting the profiled steel plate, wooden boards or soft objects should be used to cushion between the thick steel plate and the steel wire rope to avoid scratching the profiled steel plate and causing it to deform. Lift the thick steel plate onto the spherical grid and open it.

3. Before installing the irregular steel plate, the appearance quality should be checked, and the surface should be free of defects such as oil stains, fine sand, cracks, peeling, scratches, etc.

4. The overlap of the profiled steel plate should be relative to the local long-term wind frequency.

5. The installation of irregular steel plates starts from a stainless steel sink with a centerline, and the parallel plane at the eaves is pulled to a reference point of a ridge to ensure the parallelism of the eaves and the flatness with the ridge.

6. The overlapping length of the layer mesh board is 80-100mm. No need to apply sealant at the overlap. The joint of the profiled steel plate should form a parallel line from the bottom, parallel to the eaves. The joints should be symmetrical and neat, tight without shrinking.

7. The top shaped steel plate should be bent upwards by 80 ° at one end of the ridge to prevent backflow. The lap length of the top pressed steel plate should be greater than 200mm, and two sealing strips should be applied at the lap position. The joint of the profiled steel plate should be parallel to the eaves from the top. The joints should be symmetrical and neat, tight without shrinking.

8. The overlap length between the waterproof board and the edge board shall not be less than 100mm, and the overlap position shall be coated with sealant. Flash plates, edge plates, and irregular steel plates are connected with rivets. The vertical connection interval shall not exceed 50cm, and the horizontal connection interval shall not exceed 50mm. The spacing should be symmetrical, and the position of the double-sided connection should be symmetrical. Sealant should be used to seal the bolts.

9. The joint stainless steel sink, mountain wall rainproof board, and concrete or brick ring beam are used by the automatic cutting machine to cut the deep seam of the ring beam. The rainproof board at the bottom is inserted into the seam, which is sealed with sealant. The rain shelter is fixed to the girl's wall with cement steel nails, and the head of the cement steel nails is sealed with sealant.

10. A dedicated self tapping gun should be used when tapping self tapping screws. Each row of self tapping screws should be equipped with a line to form a parallel line, parallel to the ridge or eaves, to avoid drilling errors. The connection surface between steel purlins and color steel roof should be vertically divided using self tapping screws, and the tightening and loosening level of the screws should be consistent with the diameter of the waterproof pad and nail head. Do not loosen the nails or damage the waterproof mat.


1689220084333008.jpeg


Phone: (+86) 137-7105-3760

Contact person: Mr. Xiao

Address: Workshop No. 9, Baishiao No.3, Xiashan, Hengpi Town, Enping City, Guangdong Province



Navigation


Home                          Products

About                          Cases

News                          Contact





WeChat


×
seo seo